Question
1 Approved Answer
In 2024, Long Construction Corporation began construction work under a three-year contract. The contract price is $2,300,000. Long recognizes revenue over time according to percentage
In 2024, Long Construction Corporation began construction work under a three-year contract. The contract price is $2,300,000. Long recognizes revenue over time according to percentage of completion for financial reporting purposes. The financial statement presentation relating to this contract at December 31, 2024, is as follows:
Balance Sheet | ||
---|---|---|
Accounts receivable (from construction progress billings) | $ 37,000 | |
Construction in progress | $150,000 | |
Less: Billings on construction contract | (141,000) | |
Cost and profit of uncompleted contracts in excess of billings | 9,000 |
Income Statement | |
---|---|
Income (before tax) on the contract recognized in 2024 | $ 27,000 |
Required:
- What was the cost of construction actually incurred in 2024?
- How much cash was collected in 2024 on this contract?
- What was the estimated cost to complete as of the end of 2024?
- What was the estimated percentage of completion used to calculate revenue in 2024?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started