In 2024, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in

In 2024, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2026. Information related to the contract is as follows:

2024 2025 2026
Cost incurred during the year $ 2,291,000 $ 3,555,000 $ 2,259,400
Estimated costs to complete as of year-end 5,609,000 2,054,000 0
Billings during the year 1,900,000 3,946,000 4,154,000
Cash collections during the year 1,700,000 3,500,000 4,800,000

Assume that Westgate Constructions contract with Santa Clara County does not qualify for revenue recognition over time.

Required:

1. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years.

2-a. In the journal below, complete the necessary journal entries for the year 2024 (credit Cash, Materials, etc. for construction costs incurred).

2-b. In the journal below, complete the necessary journal entries for the year 2025 (credit Cash, Materials, etc. for construction costs incurred).

2-c. In the journal below, complete the necessary journal entries for the year 2026 (credit Cash, Materials, etc. for construction costs incurred).

3. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years, assuming the following costs incurred and costs to complete information.

2024 2025 2026
Cost incurred during the year $ 2,510,000 $ 3,855,000 $ 3,210,000
Estimated costs to complete as of year-end 5,710,000 3,210,000 0

4. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years, assuming the following costs incurred and costs to complete information.

2024 2025 2026
Cost incurred during the year $ 2,510,000 $ 3,855,000 $ 4,065,000
Estimated costs to complete as of year-end 5,710,000 4,210,000 0

Req 1:

2024 2025 2026
Revenue
Gross Profit (loss)

Req 2a: 2024 Journal entries

  1. Record the construction costs
  2. Record the progress billings
  3. Record the cash collections
  4. Record the gross profit (loss)

Req 2b: 2025 Journal entries

  1. Record the construction costs
  2. Record the progress billings
  3. Record the cash collections
  4. Record the gross profit (loss)

Req 2c: 2026 Journal entries

  1. Record the construction costs
  2. Record the progress billings
  3. Record the cash collections
  4. Record the gross profit (loss)

Req 3: Rev and GP using new numbers

2024 2025 2026
Revenue
Gross Profit (loss)

Req 4: Rev and GP using new numbers

2024 2025 2026
Revenue
Gross Profit (loss)

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Construction Industry IRS Audit Techniques Guide

Authors: Internal Revenue Service

1st Edition

1304131920, 978-1304131928

More Books

Students also viewed these Accounting questions

Question

How do biology and the environment influence our sleep patternspg12

Answered: 1 week ago

Question

design a simple disciplinary and grievance procedure.

Answered: 1 week ago