In a Production Capacity Chart we use the equation Capacity = Operational time per shift / (Process time setup time). If we have an 8.5
In a Production Capacity Chart we use the equation Capacity = Operational time per shift / (Process time setup time). If we have an 8.5 hour shift with a total of 45 minutes for breaks (465 minutes total available per shift) and a process time of 36.6 seconds per unit (including actual process time plus setup time) for a process what is our capacity for that process for the entire shift