Question

1 Approved Answer

In a software project a task is scheduled to take 5 days to complete and each of the 5 days are equal. Each day

In a software project a task is scheduled to take 5 days to complete and each of the 5 days are equal. Each

In a software project a task is scheduled to take 5 days to complete and each of the 5 days are equal. Each day of the 5- day task is scheduled to cost $100. At the end of the 5 days, you determine that only 3 days of the task are complete. A report tells you that he actual cost for the 5 days of effort but only 3 completed days of work was $400. Calculate the values in the following table using the given data of the project: The cost performance index The scheduled variance The schedule performance index At the current rate of progress, the task will complete at about (ETC) The estimated cost at completion (EAC)

Step by Step Solution

3.34 Rating (154 Votes )

There are 3 Steps involved in it

Step: 1

Lets calculate the requested values based on the given data 1 Cost Performance Index CPI CPI EV AC G... blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Project management the managerial process

Authors: Eric W Larson, Clifford F. Gray

5th edition

73403342, 978-0073403342

More Books

Students also viewed these General Management questions