Question
In April, Carlin, a general contractor, contracted with a town to renovate the town square. The town council wanted the project done early and the
In April, Carlin, a general contractor, contracted with a town to renovate the town square. The town council wanted the project done early and the parties placed a clause in the contract that for each day the project extended beyond 90 working days, Carlin would forfeit $88 of the contract price. In July, Carlin took a two-week vacation and stopped work during that period. The project was completed in August, 120 working days after it was begun. What type of damages may the town recover from Carlin?
Group of answer choices
Punitive damages because taking a vacation in the middle of the project was irresponsible.
Liquidated damages because of the clause in the contract.
No damages because Carlin completed performance.
Compensatory damages because of the delay in completing the project.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started