In assembly - line balancing, the theoretical minimum number of workstations is: Group of answer choices all of these. not always possible to reach when
In assemblyline balancing, the theoretical minimum number of workstations is:
Group of answer choices
all of these.
not always possible to reach when tasks are actually assigned to stations.
always when a fraction rounded upward to the next larger integer value.
the ratio of the sum of all task times to cycle time.
none of these.