Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

In December 2016, Playtime Corp. signs a contract to construct a new playground for Surrey County for $2,460,000. Construction of the new playground begins in

In December 2016, Playtime Corp. signs a contract to construct a new playground for Surrey County for $2,460,000. Construction of the new playground begins in March 2017, and is expected to be completed in August 2018. At the signing of the contract, Playtime Corp. estimates that it would cost $1,750,000 to build the playground. At the end of 2017, Playtime Corp. reports the following updated information about the project:

Costs incurred

Estimated costs

Year

to date

remaining

2017

$1,200,000

$600,000

If Playtime uses the percentage of completion to recognize revenue on the long-term contract, how much gross profit should Playtime recognize for the project in 2017?

$470,000

$410,000

$440,000

$500,000

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

More Books

Students also viewed these Finance questions