Question

1 Approved Answer

in microsoft project To lock a task to a date, instead of changing the date in the start date column, change the _ _ _

in microsoft project To lock a task to a date, instead of changing the date in the "start date" column, change the ______ to "Must Start On"
WBS code
Predecessor
Constraint type
Task Type

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Business and Administrative Communication

Authors: Kitty o. locker, Donna s. kienzler

10th edition

77830105, 978-0077830106, 978-0073403182

More Books

Students also viewed these General Management questions