Question
In spring of this year, Parmac Engineering Company signed a $192 million contract with the city of Parkersburg, to construct a new city hall. Parmac
In spring of this year, Parmac Engineering Company signed a $192 million contract with the city of Parkersburg, to construct a new city hall. Parmac expects to construct the building within two years and incur expenses of $144 million. The city of Parkersburg paid $48 million when the contract was signed, $196 million within the next six months, and the final $48 million exactly one year from the signing of the contract. Parmac incurred $58 million in costs during the year and rest in the following year to complete the contract on time.
Using the cost-to-cost method how much revenue should Parmac recognize in the current year?
A) $ 48 million
B) $ 77 million
C) $ 86 million
D) $144 million
E) None of these are correct.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started