In the meeting with a project manager, you discuss the best break-even analysis tool to use that takes into consideration time value of money. Which
In the meeting with a project manager, you discuss the best break-even analysis tool to use that takes into consideration time value of money. Which tool is discussed?
A. Accounting break-even
B. Cash break-even
C. NPV break-even
D. IRR break-even
Explanation for answer please.