In the process of scheduling begins as soon as requirements are known to avoid activity overlap and resource constraints. Reverse scheduling Forward scheduling Priority scheduling
In the process of scheduling begins as soon as requirements are known to avoid activity overlap and resource constraints.
Reverse scheduling
Forward scheduling
Priority scheduling
Backward scheduling