Question

1 Approved Answer

Inspection time 0.2 days Wait time (from order to start of production) 17.1 days Process time 3.5 days Move time 0.9 days Queue time 3.8

Inspection time 0.2 days
Wait time (from order to start of production) 17.1 days
Process time 3.5 days
Move time 0.9 days
Queue time 3.8 days
Requirement 1:
Compute the throughput time. (Round your answer to 1 decimal place.)
Throughput time days
Requirement 2:
Compute the manufacturing cycle efficiency (MCE) for the quarter. (Round your answer to 2 decimal place.)

Manufacturing cycle efficiency
Requirement 3:

What percentage of the throughput time was spent in non-value-added activities? (Round your answer to the nearest whole number.)

Throughput time %
Requirement 4:
Compute the delivery cycle time.(Round your answer to 1 decimal place.)
Delivery cycle time days
Requirement 5:

If by using Lean Production all queue time during production is eliminated, what will be the new MCE?(Round your answer to 3 decimal places.)

Manufacturing cycle efficiency

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Emile Woolf On Audit Exemption

Authors: Emile Woolf

1st Edition

0863253911, 978-0863253911

More Books

Students also viewed these Accounting questions