Instant Dolls specializes in making custom dolls on a make - to - order basis. Their product is popular so that there is always sufficient

Instant Dolls specializes in making custom dolls on a make-to-order basis. Their product is popular so that there is always sufficient demand to match capacity. The service process includes the following steps performed in sequence (time in parenthesis):
Activity 1: Get the specifications of the doll from the customer, get the payment, and submit the order to the production line. (8 min)
Activity 2: Assemble the main body of the doll (10 min)
Activity 3: Add hair and paint (14 min)
Activity 4: Dress doll (15 min)
Activity 5: Pack doll (3 min)
There are three workers (S1, S2, and S3) in the whole process. They divide the work in the following way:
S1 does Activity 1
S2 does Activity 2 and Activity 3
S3 does Activity 4 and Activity 5
Instant dolls earn $30 per doll (after deducting the cost of raw materials but before labor costs). Each worker costs $20/ hour. The factory opens sufficiently long so that effective capacity is almost the same as design capacity.
Use all the information given here to answer the following questions

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Management Process

Authors: Lee Long

4th Edition

978-0201822939,0201822938

More Books

Students also viewed these General Management questions