Question: It takes an operator 2 min to service a machine. Each machine runs automatically for 7 min. Graphically represent the operator machine activities if
It takes an operator 2 min to service a machine. Each machine runs automatically for 7 min. Graphically represent the operator machine activities if you round the number of machines up? (3 points)
Step by Step Solution
3.40 Rating (150 Votes )
There are 3 Steps involved in it
Answer hence operator can service 3 mc Given Time taken to service takon ... View full answer