Question: It takes an operator 2 min to service a machine. Each machine runs automatically for 7 min. Graphically represent the operator machine activities if

It takes an operator 2 min to service a machine. Each machine runs automatically for 7 min. Graphically  

It takes an operator 2 min to service a machine. Each machine runs automatically for 7 min. Graphically represent the operator machine activities if you round the number of machines up? (3 points)

Step by Step Solution

3.40 Rating (150 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

Answer hence operator can service 3 mc Given Time taken to service takon ... View full answer