Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

its Q27 cashflow text book Modren construction management 7th edition Frank Harris and Ronald McCaffer The programme for the construction of a small workshop building

image text in transcribed

its Q27 cashflow text book Modren construction management 7th edition Frank Harris and Ronald McCaffer

The programme for the construction of a small workshop building is displayed in the form of a precedence diagram, shown in Fig. The value of the work contained in each activity has been calculated from the rates contained in the bill of quantities and is listed in Table. 1.5 min ARBE HBB Durations in months Overlap between finish of X and start of Y Precedence diagram for construction of a workshop. Activities Duration (months) Value () A Excavate 2 9 000 12 000 1.5 18 000 B Concrete base 3 CErect frames D Concrete floor slabs 1 E Fix cladding F Install plant 15 000 1.5 6 000 20 000 1 Note: Rate of work throughout any activity is uniform. Value of activities (1) The contractor undertaking the project would like you to prepare a table of cumulative cost and monies received to date against time for activities starting as early as possible, in order to establish a clearer picture of the financial implications of this contract. From these graphs, calculate the net profit if interest is charged at 8% p.a. on outstanding monies. The gross profit margin is 10% of contract value and retention is 5% up to a maximum limit of 3000. Measurement is made monthly with a payment delay of one month. Half of the retention is paid on practical completion and the remaining half six months later. To simplify the calculation, you may assume that all costs must be met at the instant they are incurred. (2) What is the maximum amount of cash the contractor needs in order to execute this contract and when does the contractor require this amount? The programme for the construction of a small workshop building is displayed in the form of a precedence diagram, shown in Fig. The value of the work contained in each activity has been calculated from the rates contained in the bill of quantities and is listed in Table. 1.5 min ARBE HBB Durations in months Overlap between finish of X and start of Y Precedence diagram for construction of a workshop. Activities Duration (months) Value () A Excavate 2 9 000 12 000 1.5 18 000 B Concrete base 3 CErect frames D Concrete floor slabs 1 E Fix cladding F Install plant 15 000 1.5 6 000 20 000 1 Note: Rate of work throughout any activity is uniform. Value of activities (1) The contractor undertaking the project would like you to prepare a table of cumulative cost and monies received to date against time for activities starting as early as possible, in order to establish a clearer picture of the financial implications of this contract. From these graphs, calculate the net profit if interest is charged at 8% p.a. on outstanding monies. The gross profit margin is 10% of contract value and retention is 5% up to a maximum limit of 3000. Measurement is made monthly with a payment delay of one month. Half of the retention is paid on practical completion and the remaining half six months later. To simplify the calculation, you may assume that all costs must be met at the instant they are incurred. (2) What is the maximum amount of cash the contractor needs in order to execute this contract and when does the contractor require this amount

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Conservation Easement IRS Audit Techniques Guide

Authors: Internal Revenue Service

1st Edition

1304133923, 978-1304133922

More Books

Students also viewed these Accounting questions

Question

f. Did they change their names? For what reasons?

Answered: 1 week ago