Answered step by step
Verified Expert Solution
Question
1 Approved Answer
its Q27 cashflow text book Modren construction management 7th edition Frank Harris and Ronald McCaffer The programme for the construction of a small workshop building
its Q27 cashflow text book Modren construction management 7th edition Frank Harris and Ronald McCaffer
The programme for the construction of a small workshop building is displayed in the form of a precedence diagram, shown in Fig. The value of the work contained in each activity has been calculated from the rates contained in the bill of quantities and is listed in Table. 1.5 min ARBE HBB Durations in months Overlap between finish of X and start of Y Precedence diagram for construction of a workshop. Activities Duration (months) Value () A Excavate 2 9 000 12 000 1.5 18 000 B Concrete base 3 CErect frames D Concrete floor slabs 1 E Fix cladding F Install plant 15 000 1.5 6 000 20 000 1 Note: Rate of work throughout any activity is uniform. Value of activities (1) The contractor undertaking the project would like you to prepare a table of cumulative cost and monies received to date against time for activities starting as early as possible, in order to establish a clearer picture of the financial implications of this contract. From these graphs, calculate the net profit if interest is charged at 8% p.a. on outstanding monies. The gross profit margin is 10% of contract value and retention is 5% up to a maximum limit of 3000. Measurement is made monthly with a payment delay of one month. Half of the retention is paid on practical completion and the remaining half six months later. To simplify the calculation, you may assume that all costs must be met at the instant they are incurred. (2) What is the maximum amount of cash the contractor needs in order to execute this contract and when does the contractor require this amount? The programme for the construction of a small workshop building is displayed in the form of a precedence diagram, shown in Fig. The value of the work contained in each activity has been calculated from the rates contained in the bill of quantities and is listed in Table. 1.5 min ARBE HBB Durations in months Overlap between finish of X and start of Y Precedence diagram for construction of a workshop. Activities Duration (months) Value () A Excavate 2 9 000 12 000 1.5 18 000 B Concrete base 3 CErect frames D Concrete floor slabs 1 E Fix cladding F Install plant 15 000 1.5 6 000 20 000 1 Note: Rate of work throughout any activity is uniform. Value of activities (1) The contractor undertaking the project would like you to prepare a table of cumulative cost and monies received to date against time for activities starting as early as possible, in order to establish a clearer picture of the financial implications of this contract. From these graphs, calculate the net profit if interest is charged at 8% p.a. on outstanding monies. The gross profit margin is 10% of contract value and retention is 5% up to a maximum limit of 3000. Measurement is made monthly with a payment delay of one month. Half of the retention is paid on practical completion and the remaining half six months later. To simplify the calculation, you may assume that all costs must be met at the instant they are incurred. (2) What is the maximum amount of cash the contractor needs in order to execute this contract and when does the contractor require this amountStep by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started