Answered step by step
Verified Expert Solution
Question
1 Approved Answer
JE's: Req 4: Req 5: THANKS!!! In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for
JE's:
Req 4:
Req 5:
THANKS!!!
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2023 $2,655,400 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $ 1,491,000 5,609,000 1,100,000 900,000 2022 $3,195,000 2,414,000 3,586,000 2,700,000 5,314,000 6,400,000 Assume that Westgate Construction's contract with Santa Clara County does not qualify for revenue recognition over time. Required: 1. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years. 2-a. In the journal below, complete the necessary journal entries for the year 2021 (credit "Various accounts" for construction costs incurred). 2-b. In the journal below, complete the necessary journal entries for the year 2022 (credit "Various accounts" for construction costs incurred). 2-c. In the journal below, complete the necessary journal entries for the year 2023 (credit "Various accounts" for construction costs incurred). 3. Complete the information required below to prepare a partial balance sheet for 2021 and 2022 showing any items related to the contract. 4. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years assuming the following costs incurred and costs to complete information. 2021 2022 2023 Cost incurred during the year $2,590,000 $3,895,000 $3,290,000 Estimated costs to complete as of year-end 5,790,000 3,290,000 5. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years assuming the following costs incurred and costs to complete information. Cost incurred during the year Estimated costs to complete as of year-end 2021 $2,590,000 5,790,000 2022 $3,895,000 4,290,000 2023 $4,185,000 Record the construction costs. Record the progress billings. Record the cash collections. Record the gross profit (loss). 2021 2022 Balance Sheet (Partial) Current assets: Current liabilities: Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years using the above information. (Leave no cells blank - be certain to enter "0" wherever required. Loss amounts should be indicated with a minus sign.) 2021 2022 2023 Revenue Gross profit (loss) Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years using the above information. (Leave no cells blank - be certain to enter "0" wherever required. Loss amounts should be indicated with a minus sign.) 2021 2022 2023 Revenue Gross profit (loss)Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started