Question
just need answers 1)On-demand scheduling approach is typically used in aKanban system Group of answer choices True False 2) Activities is the process of identifying
just need answers
1)On-demand scheduling approach is typically used in aKanban system
Group of answer choices
True
False
2) Activities is the process of identifying and documenting thespecific actions to be performed to produce the projectdeliverables.
Group of answer choices
True
False
3) Finish-to-start (FS) is A logical relationship in which a successor activitycannot start until a predecessor activity has finished.
Group of answer choices
True
False
4) Alagis the amount of time a successor activity can beadvanced with respect to a predecessor activity.
Group of answer choices
True
False
5) Triangular distribution Formula is :
tE= (tO+tM+tP) / 10.
Group of answer choices
True
False
6) In fistoffive (also called fist to five) technique, the project manager asks the team to showtheir level of support for a decision by holding up a closed fist
Group of answer choices
True
False
7) What-if scenario analysis is the processof evaluating scenariosin order topredict their effect, positive ornegative, on project objectives.
Group of answer choices
True
False
8) Critical Path Analysis is the shortest sequence of activities in a projectschedule
Group of answer choices
True
False
9) Total float is the amount of time an activity may bedelayed before it delays the project end date
Group of answer choices
True
False
10) Approaches to estimating costs include:
- Analogous
- Parametric
- Bottom-Up
Group of answer choices
True
False
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started