Question
Keego Enterprises manufactures two products, boat wax and car wax, in two departments, Mixing and Packaging. The Mixing Department has 800 hours per month available
Keego Enterprises manufactures two products, boat wax and car wax, in two departments, Mixing and Packaging. The Mixing Department has 800 hours per month available while the Packaging Department has 1,200 hours per month available. Production of the two products cannot exceed 36,000 pounds. Data on the two products follow:
| Contribution Margin (per 100 pounds) | Hours per 100 Mixing (M) | Pounds of Output Packaging (P) |
Boat wax (B) | $200 | 5.0 | 3.6 |
Car wax (C) | $150 | 2.4 | 6.0 |
The objective function for the linear program Keego would use to determine the optimum monthly product mix would be:
A. | Z = $150B + $200C. |
B. | 2B + 1.5C 36,000. |
C. | 2B + 1.5C 36,000. |
D. | Z = $200B + $150C. |
E. | Z = 8.6B + 8.4B. |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started