Question
Kekerovic Contractors specialises in the planning and construction of houses in Nimes, southern France. The operations director, Bronco Kekerovic, has recently taken on a project
A - Lay foundation to the house: 1 week.
B- Construction of house: 6 weeks. B is preceded by A.
C - Excavation, and foundation for swimming pool: 2 weeks.
C is preceded by A.
D - Tiling and sealing of pool: 2 weeks. Dis preceded by C.
E - Internal decor and fixtures for the house: 3 weeks. E is preceded by B.
F- Final testing and handing over keys to the new owner: 1 week. F is preceded by activities D and E.
(a} Construct a Gantt chart for Kekerovic Contractors using the above information and identify the quickest time in which the project can be completed. [5 marks}
(b) Explain why the use of Gantt charts can be important for businesses such as Kekerovic Contractors.
Step by Step Solution
3.57 Rating (171 Votes )
There are 3 Steps involved in it
Step: 1
a Gantt Chart for Kekerovic Contractors Task Duration weeks Predecessors Start Date End Date A Lay f...Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3