Kekerovic Contractors specialises in the planning and construction of houses in Nimes, southern France. The operations director, Bronco Kekerovic, has recently taken on a project

Kekerovic Contractors specialises in the planning and construction of houses in Nimes, southern France. The operations director, Bronco Kekerovic, has recently taken on a project to build a four-bedroom home with an outdoor pool. The project's tasks, duration, and sequence are outlined below.

A - Lay foundation to the house: 1 week.

B- Construction of house: 6 weeks. B is preceded by A.

C - Excavation, and foundation for swimming pool: 2 weeks.

C is preceded by A.

D - Tiling and sealing of pool: 2 weeks. Dis preceded by C.

E - Internal decor and fixtures for the house: 3 weeks. E is preceded by B.  

F- Final testing and handing over keys to the new owner: 1 week. F is preceded by activities D and E.

(a} Construct a Gantt chart for Kekerovic Contractors using the above information and identify the quickest time in which the project can be completed. [5 marks}

(b) Explain why the use of Gantt charts can be important for businesses such as Kekerovic Contractors.

Step by Step Solution

3.57 Rating (171 Votes )

There are 3 Steps involved in it

Step: 1

a Gantt Chart for Kekerovic Contractors Task Duration weeks Predecessors Start Date End Date A Lay f... blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Engineering Economy

Authors: William G. Sullivan, Elin M. Wicks, C. Patrick Koelling

16th edition

133439275, 133439274, 9780133819014 , 978-0133439274

More Books

Students also viewed these General Management questions