Answered step by step
Verified Expert Solution
Question
1 Approved Answer
Kennywood Inc., a manufacturing firm, is able to produce 1,100 pairs of pants per hour, at maximum efficiency. There are three eight hour shifts each
Kennywood Inc., a manufacturing firm, is able to produce 1,100 pairs of pants per hour, at maximum efficiency. There are three
eighthour
shifts each day. Due to unavoidable operating interruptions, production averages 825 units per hour. The plant actually operates only 28 days per month. Based on the current budget, Kennywood estimates that it will be able to sell only 504,000 units due to the entry of a competitor with aggressive marketing capabilities. But the demand is unlikely to be affected in future and will be around 515,000. Assume the month has 30 days. What is the theoretical capacity for the month? A.
554,400 units
B.
739,200 units
C.
222,750 units
D.
792,000 units
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started