Activity | Normal Time (weeks) | Crash Time (weeks) | Normal Cost | Total Cost with crashing | Immediate Predecessor(s) |
A | 3 | 2 | $1200 | $1800 | |
B | 2 | 1 | $2300 | $3000 | |
C | 1 | 1 | $350 | $350 | |
D | 7 | 3 | $1300 | $1580 | A |
E | 6 | 3 | $950 | $1100 | B |
F | 2 | 1 | $4250 | $5450 | C |
G | 4 | 2 | $1800 | $2500 | D, E |
a) Based on the given information regarding the activities for the project, the project completion date = ? weeks.
b) For reducing the duration of the project to 10 weeks at the least cost, following is the order of that needs to be followed while crashing the activities:
The first activity to crash is ? by 2 weeks at a per week crashing cost of ? dollars.
Next, one should crash activity D and activity ? by 2 weeks each at a total per week crashing cost of ? dollows.
c) New requirements are to reduce the project to 7 weeks. Continuing to crash the activities from 10 weeks based on the above crashing already completed, following is the order for crashing:
Next activity to crash in order is ? by 2 weeks at a per week crashing cost of ? dollars.
Next, one should crash activity ? and activity E by 1 week at a total per week crashing cost of ? dollars.
Total cost of crashing the project to 7 weeks = ? dollars.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started