King Inc. began work in 2018 on a contract for P8,400,000. Other data are as follows:

2018 2019

Cost Incurred 3,600,000.00 5,600,000.00

Estimated costs to Complete 2,400,000.00

Billings during the year 2,800,000.00 8,400,000.00

Collections to date 2,000,000.00 7,200,000.00

1. Using the percentage of completion method, what is the gross profit to be recognized in 2018?

2. Using the percentage of completion method, what is the gross profit to be recognized in 2019?

3. Using the recovery method, what is the gross profit to be recognized in 2018?

4. Using the recovery method, what is the gross profit to be recognized in 2019?

5. What is the balance in the Construction in progress account at the end of 2018 using the percentage of completion method?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Modern Advanced Accounting in Canada

Authors: Hilton Murray, Herauf Darrell

8th edition

1259087557, 1057317623, 978-1259087554

More Books

Students also viewed these Accounting questions