Kumar adds a finish no later than date constraint to his schedule. Two activities now show that they will finish later than the project complete

Kumar adds a "finish no later than" date constraint to his schedule. Two activities now show that they will finish later than the project complete milestone. How can he address this negative slack?

Select an answer:

  • Change the critical threshold setting to the lowest total slack value in the schedule.
  • Rework the dates for all the activities on the critical path in the schedule.
  • Redefine which tasks in the schedule are on the critical path and which ones are not.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

To address the negative slack issue where two activities are finishing later than the project comple... blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Income Tax Fundamentals 2013

Authors: Gerald E. Whittenburg, Martha Altus Buller, Steven L Gill

31st Edition

1111972516, 978-1285586618, 1285586611, 978-1285613109, 978-1111972516

More Books

Students also viewed these General Management questions