Legend: Project Network Diagram Baseline Information: Answer by Completing this Status Report End of Period 4 Task Actual % Complete EV$ AC$ PV$ CV$ SV$

Legend:
Project Network Diagram
Baseline Information:
Answer by Completing this Status Report
End of Period 4
Task Actual % Complete EV$ AC$ PV$ CV$ SV$
A Finished ?300400??
B 50%?1000800??
C 33% or 1/3 of the Budget ?500600??
D 0%?0???
E 0%?????
Cumulative Totals ?????
End of Period 8
Task Actual % Complete EV$ AC$ PV$ CV$ SV$
A Finished ?300400??
B Finished ?22002400??
C Finished ?15001500??
D 25%?3000??
E 33% or 1/3 of the budget ?300???
F 0%?0???
Cumulative Totals ?????

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image
Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Management

Authors: Stephen P Robbins, Mary Coulter

11th Edition

9780273752776, 132163845, 273752774, 978-0132163842

More Books

Students explore these related General Management questions