Question
Levy Furniture, a furniture manufacturer is planning a factory expansion project. The activities required, their immediate predecessors, and the optimistic, most likely, and pessimistic estimates
Levy Furniture, a furniture manufacturer is planning a factory expansion project. The activities required, their immediate predecessors, and the optimistic, most likely, and pessimistic estimates of their times (in days) are provided below. The project network is also provided.
Activity | Description | Immediate Predecessors | Optimistic Time (days) | Most Likely Time (days) | Pessimistic Time (days) |
A | Develop initial plans | -- | 2 | 2.5 | 6 |
B | Secure financing | A | 1 | 2 | 3 |
C | Develop final plans | A | 2 | 3 | 10 |
D | Hire contractor | C | 1 | 3 | 5 |
E | Secure permits | C | 1 | 4 | 7 |
F | Construct addition | B,D,E | 3 | 11 | 13 |
G | Order equipment | A | 6 | 11 | 22 |
H | Install equipment | F,G | 1 | 3 | 5 |
Show all calculations and work.
a) Construct the project network.
b) Identify the critical path and provide the project completion time.
c) Calculate the slack time for each activity and for each path (relative to the critical path).
d) Looking at only the critical path, find the probability that the store will take 26 or more working days to open.
e) What is the probability of completing path ACEFH in time for the store to open in 24 working days or less?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started