Question
Lido Company's standard and actual costsfor the most recent period, are given below: Lido uses the following manufacturing standards Per Unit: *Direct Material: 2metres @$1.56
Lido Company's standard and actual costsfor the most recent period, are given below:
Lido uses the following manufacturing standards Per Unit:
*Direct Material: 2metres @$1.56 per metre
*Direct Labour : 1.25Hours @ $16.00per hour
*MOH:Variable: 1.25Hours @ $3.45 per DLH
-Fixed: 1.25 Hrs @$10.00 based on capacity to produce 1,000 units
During the most recent period Lido provided the following details:
Produced 950 Units
Raw Material:
- 2,500 metres of material were purchased at $1.45 per metre, and 2,000 metres were used
Direct Labour:
- 1,420 hours oflabour wereassigned to produce 950 units. Direct labour actual hourly rate was $16.65
Actual Variable Manufacturing Overhead - MOH:
- $3.70 per labour hour.Direct Labour Hours- DLH asthe COST DRIVER foroverheadapplication.
Actual Fixed Overhead amounted to $11,500 for theperiod
Attached to this case, is an Excel Spreadsheet with imbedded formulas designed to calculate the variances for: Direct Material - DM; Direct Labour - DL; VariableManu-facturing Overhead - MOH VC; Fixed Manufacturing Overhead - MOH FC
All the Variances have been determined.
QUESTIONS
Part I: Provide Journal Entries for:
1. The purchase and use of raw materials
2. Direct Labour
Part II: Complete the following variance report and perform the analysis that follows
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started