Lowell Manufacturing Company uses a job-order costing system and started the month of October with a zero balance in its work in process and finished

Lowell Manufacturing Company uses a job-order costing system and started the month of October with a zero balance in its work in process and finished goods inventory accounts. During October, Lowell worked on three jobs and incurred the following:

Job B18 Job B19 Job C11
Direct materials $12,000 $25,000 $18,000
Direct labor cost $8,000 $10,000 $5,000
Direct labor hours 400 hours 500 hours 250 hours

Lowell pays direct laborers at $20 per hour. Lowell applies manufacturing overhead at a rate of $15 per direct labor hour. During October, Lowell completed Jobs B18 and B19 and sold Job B19.

What is the total cost assigned to Job 18?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Innovation Audit Workbook

Authors: Langdon Morris

1st Edition

B08HBBKKPJ, 979-8682091614

More Books

Students also viewed these Accounting questions