Lungy has just been assigned as the project manager for a website development project. Mark, the project sponsor has handed over a signed Project Charter
Lungy has just been assigned as the project manager for a website development project. Mark, the project sponsor has handed over a signed Project Charter to Lungy authorizing her as the project manager of this project. What should be the next step for Lungy?
A Develop the Project Management Plan
B Plan project communications
C Hire the project team
D Identify project stakeholders