Mahaley, Incorporated, manufactures and sells two products: Product Q9 and Product F0. Data concerning the expected production of each product and the expected total direct

Mahaley, Incorporated, manufactures and sells two products: Product Q9 and Product F0. Data concerning the expected production of each product and the expected total direct labor-hours (DLHs) required to produce that output appear below:

Expected Production Direct Labor-Hours Per Unit Total Direct Labor-Hours
Product Q9 920 9.2 8,464
Product F0 920 7.2 6,624
Total direct labor-hours 15,088

The direct labor rate is $23.00 per DLH. The direct materials cost per unit for each product is given below:

Direct Materials Cost per Unit
Product Q9 $ 176.10
Product F0 $ 147.90

The company is considering adopting an activity-based costing system with the following activity cost pools, activity measures, and expected activity:

Activity Cost Pools Activity Measures Estimated Overhead Cost Expected Activity
Product Q9 Product F0 Total
Labor-related DLHs $ 391,680 8,464 6,624 15,088
Machine setups setups 49,830 900 800 1,700
Order size MHs 290,700 4,300 4,100 8,400
$ 732,210

The unit product cost of Product F0 under activity-based costing is closest to: (Round your intermediate calculations to 2 decimal places.)

Multiple Choice

$754.34 per unit

$680.14 per unit

$387.70 per unit

$514.54 per unit

Snavely, Incorporated, manufactures and sells two products: Product E1 and Product A7. Data concerning the expected production of each product and the expected total direct labor-hours (DLHs) required to produce that output appear below:

Expected Production Direct Labor-Hours Per Unit Total Direct Labor-Hours
Product E1 900 10.0 9,000
Product A7 600 5.0 3,000
Total direct labor-hours 12,000

The direct labor rate is $25.90 per DLH. The direct materials cost per unit for each product is given below:

Direct Materials Cost per Unit
Product E1 $ 284.00
Product A7 $ 240.00

The company has an activity-based costing system with the following activity cost pools, activity measures, and expected activity:

Activity Cost Pools Activity Measures Estimated Overhead Cost Expected Activity
Product E1 Product A7 Total
Labor-related DLHs $ 120,900 9,000 3,000 12,000
Machine setups setups 57,020 1,000 600 1,600
Order size MHs 891,840 4,000 2,600 6,600
$ 1,069,760

The total overhead applied to Product A7 under activity-based costing is closest to: (Round your intermediate calculations to 2 decimal places.)

Multiple Choice

$666,880

$177,920

$351,338

$402,962

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Cornerstones Of Financial And Managerial Accounting Fnec 220

Authors: Jay S. Rich, Jeff Jones, Dan L. Heitger, Maryanne M. Mowen, Don R. Hansen

2nd Edition

1133275583, 978-1133275589

More Books

Students also viewed these Accounting questions

Question

=+ Are there additional forms of employee representation?

Answered: 1 week ago