Management has been informed of a risk to personally identifiable information (PII) that results from an application being developed and managed by the company. They
Management has been informed of a risk to personally identifiable information (PII) that results from an application being developed and managed by the company. They have chosen not to do anything with the risk. What risk management approach have they taken? Group of answer choices Risk transference Risk mitigation Risk acceptance Risk avoidance