Question

1 Approved Answer

Management of Mittel Company wants to reduce the elapsed time from when a customer places an order to when it is shipped. It provided the

Management of Mittel Company wants to reduce the elapsed time from when a customer places an order to when it is shipped. It provided the following data for a recent quarter:

Inspection time 0.7 day
Wait time (from order to start of production) 15.2 days
Process time 2.5 days
Move time 0.6 day
Queue time 3.7 days

Required:

  1. Compute the throughput time.

Note: Round your answer to 1 decimal place.

  1. Compute the manufacturing cycle efficiency (MCE) for the quarter.

Note: Round your percentage answer to nearest whole percent.

  1. What percentage of the throughput time was spent in nonvalue-added activities?

Note: Round your percentage answer to nearest whole percent.

  1. Compute the delivery cycle time.

Note: Round your intermediate calculations and final answer to 1 decimal place.

  1. If using Lean Production eliminates all queue time, what will be the new MCE?

Note: Do not round intermediate calculations. Round your percentage answer to 1 decimal place.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Managerial Accounting

Authors: John J. Wild, Ken W. Shaw

2010 Edition

9789813155497, 73379581, 9813155493, 978-0073379586

More Books

Students also viewed these Accounting questions

Question

Describe the goal of cognitive psychotherapy.

Answered: 1 week ago

Question

What are the five statistics that make up the five-number summary?

Answered: 1 week ago