Answered step by step
Verified Expert Solution
Question
1 Approved Answer
Management of Mittel Company wants to reduce the elapsed time from when a customer places an order to when it is shipped. It provided the
Management of Mittel Company wants to reduce the elapsed time from when a customer places an order to when it is shipped. It provided the following data for a recent quarter:
Inspection time | 0.7 | day |
---|---|---|
Wait time (from order to start of production) | 15.2 | days |
Process time | 2.5 | days |
Move time | 0.6 | day |
Queue time | 3.7 | days |
Required:
- Compute the throughput time.
Note: Round your answer to 1 decimal place.
- Compute the manufacturing cycle efficiency (MCE) for the quarter.
Note: Round your percentage answer to nearest whole percent.
- What percentage of the throughput time was spent in nonvalue-added activities?
Note: Round your percentage answer to nearest whole percent.
- Compute the delivery cycle time.
Note: Round your intermediate calculations and final answer to 1 decimal place.
- If using Lean Production eliminates all queue time, what will be the new MCE?
Note: Do not round intermediate calculations. Round your percentage answer to 1 decimal place.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started