Management of Mittel Rhein AG of Kln, Germany, would like to reduce the amount of time between when a customer places an order and when

Management of Mittel Rhein AG of Kln, Germany, would like to reduce the amount of time between when a customer places an order and when the order is shipped. For the first quarter of operations during the current year the following data were reported:

Inspection time 0.7 day
Wait time (from order to start of production) 15.2 days
Process time 3.4 days
Move time 0.7 day
Queue time 3.6 days

image text in transcribedimage text in transcribed

Required: 1. Compute the throughput time. (Round your answer to 1 decimal place.) Throughput time days 2. Compute the manufacturing cycle efficiency (MCE) for the quarter. (Round your percentage answer to nearest whole percent.) Manufacturing cycle efficiency 3. What percentage of the throughput time was spent in non-value-added activities? (Round your percentage answer to nearest whole percent.) Non-value-added throughput time 4. Compute the delivery cycle time. (Round your intermediate calculations and final answer to 1 decimal place.) Delivery cycle time days 5. If by using Lean Production all queue time during production is eliminated, what will be the new MCE? (Do not round intermediate calculations. Round your percentage answer to nearest whole percent.) New manufacturing cycle efficiency

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Patient Centered Audit

Authors: Kruse

1st Edition

0875272479, 978-0875272474

More Books

Students also viewed these Accounting questions