Management of Mittel Rhein AG of Kln, Germany, would like to reduce the amount of time between when a customer places an order and when
Management of Mittel Rhein AG of Kln, Germany, would like to reduce the amount of time between when a customer places an order and when the order is shipped. For the first quarter of operations during the ak r i aurentormer places an o 0.8 days Inspection time Wait time (from order to start of production) Process time Move time Queue time 16.8 days 3.3 days 0.9 days 4.2 days