Management of Mittel Rhein AG of Kln, Germany, would like to reduce the amount of time between when a customer places an order and when

Management of Mittel Rhein AG of Kln, Germany, would like to reduce the amount of time between when a customer places an order and when the order is shipped. For the first quarter of operations during the current year the following data were reported:

Inspection time 0.7 days
Wait time (from order to start of production) 15.7 days
Process time 2.9 days
Move time 0.8 days
Queue time 3.6 days

Required:

1. Compute the throughput time. (Round your answer to 1 decimal place.)

2. Compute the manufacturing cycle efficiency (MCE) for the quarter. (Round your percentage answer to nearest whole percent.)

3. What percentage of the throughput time was spent in nonvalue-added activities? (Round your percentage answer to nearest whole percent.)

4. Compute the delivery cycle time. (Round your intermediate calculations and final answer to 1 decimal place.)

5. If by using Lean Production all queue time during production is eliminated, what will be the new MCE? (Do not round intermediate calculations. Round your percentage answer to 1 decimal place.)

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Audits Of 401k Plans

Authors: Deloitte And Touche

2nd Edition

1119722039, 978-1119722038

More Books

Students also viewed these Accounting questions

Question

2. What is the meaning and definition of Banking?

Answered: 1 week ago

Question

3.What are the Importance / Role of Bank in Business?

Answered: 1 week ago