Question

1 Approved Answer

Mary Jones is a contract project manager with her PMP certification. She recently accepted a contract as a senior project manager for a toxic-waste disposal

Mary Jones is a contract project manager with her PMP certification. She recently accepted a contract as a senior project manager for a toxic-waste disposal company. She was uneasy at first in accepting this contract, as she had no prior experience in the toxic waste field, but she really could use the money. She figured out that she could do some quick research on the internet, become familiar with the terminology and just "fake it". What PMI Code of Ethics and Professional Conduct value (mandatory or aspirational standard) is Mary not following?

a. Honesty b. Responsibility c. Fairness d. Respect

Explain why to choose that response

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Strategic Management Text And Cases

Authors: Gregory Dess , Gerry McNamara , Alan Eisner , Steve Sauerwald

11th Edition

1264124325, 978-1264124329

More Books

Students also viewed these General Management questions