Matt Webb needs to determine whether the proposed online store project can be completed in time for the holiday shopping season. A new project manager,
Matt Webb needs to determine whether the proposed online store project can be completed in time for the holiday shopping season. A new project manager, Chris Johnson, has taken over the management of the project. He has all of the components of the plan, but he needs to integrrate them and is looking to quickly come up with an answer.
What is the project completion time? Assume there are no holidays.