Megah Holding Sdn. Bhd is in progress to start their housing project. The list of activity and scheduled of the project is proposed as in

Megah Holding Sdn. Bhd is in progress to start their housing project. The list of activity and scheduled of the project is proposed as in Table 1.

  1. If the indirect costs for each duration is as follows, compute the direct and total cost for each duration. What is the optimum cost-time schedule?

Indirect cost

27 weeks RM 350

26 weeks RM 270

25 weeks RM 160

24 weeks RM 100

12 weeks RM 70

(12 marks)

  1. An incentive of RM20 per week has been offered by your clients if you can shorten the duration of the project. Would you grab the opportunity? If yes, for how many weeks? (3 marks)

Table 1 Housing Project Schedule

Activity

Predecessor

Normal time

Normal cost

Crash cost (slope)

Maximum crash time

A

-

10

40

80

2

B

-

8

10

30

3

C

-

5

80

40

1

D

A

11

50

50

2

E

C

15

100

100

4

F

B, D, E

6

20

30

1

*Time unit = 1 week

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

The Audit Of Maritime Brokerage Companies

Authors: Aymen Karma

1st Edition

6203599743, 978-6203599749

More Books

Students also viewed these Accounting questions