Megah Holding Sdn. Bhd is in progress to start their housing project. The list of activity and scheduled of the project is proposed as in
Megah Holding Sdn. Bhd is in progress to start their housing project. The list of activity and scheduled of the project is proposed as in Table 1.
- If the indirect costs for each duration is as follows, compute the direct and total cost for each duration. What is the optimum cost-time schedule?
Indirect cost
27 weeks RM 350
26 weeks RM 270
25 weeks RM 160
24 weeks RM 100
12 weeks RM 70
(12 marks)
- An incentive of RM20 per week has been offered by your clients if you can shorten the duration of the project. Would you grab the opportunity? If yes, for how many weeks? (3 marks)
Table 1 Housing Project Schedule
Activity | Predecessor | Normal time | Normal cost | Crash cost (slope) | Maximum crash time |
A | - | 10 | 40 | 80 | 2 |
B | - | 8 | 10 | 30 | 3 |
C | - | 5 | 80 | 40 | 1 |
D | A | 11 | 50 | 50 | 2 |
E | C | 15 | 100 | 100 | 4 |
F | B, D, E | 6 | 20 | 30 | 1 |
*Time unit = 1 week
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started