Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

Mello Manufacturing Company is a diversified manufacturer that manufactures three products (Alpha, Beta, and Omega) in a continuous production process. Senior management has asked the

Mello Manufacturing Company is a diversified manufacturer that manufactures three products (Alpha, Beta, and Omega) in a continuous production process. Senior management has asked the controller to conduct an activity-based costing study. The controller identified the amount of factory overhead required by the critical activities of the organization as follows:

1

Activity

Activity Cost Pool

2

Production

$251,598.00

3

Setup

92,035.00

4

Material handling

10,736.00

5

Inspection

49,833.00

6

Product engineering

136,230.00

7

Total

$540,432.00

The activity bases identified for each activity are as follows:

Activity

Activity Base

Production Machine hours
Setup Number of setups
Material handling Number of parts
Inspection Number of inspection hours
Product engineering Number of engineering hours

The activity-base usage quantities and units produced for the three products were determined from corporate records and are as follows:

Machine Number of Number of Number of Number of
Hours Setups Parts Inspection Hours Engineering Hours Units
Alpha 970 63 84 489 123 1,354
Beta 802 123 138 272 170 1,044
Omega 435 209 266 256 185 452
Total 2,207 395 488 1,017 478 2,850

Each product requires 40 minutes per unit of machine time.

Required:
Complete the Activity Tables for Alpha, Beta and Omega.
1. Determine the activity rate for each activity.*
2. Use the activity rates in (1) to determine the total and per-unit activity costs associated with all three products.*
3. Why arent the activity unit costs equal across all three products since they require the same machine time per unit?
*If required, round all per-unit amounts to the nearest cent.

Activity Table - Alpha

Shaded cells have feedback.

Complete the Activity Table for Alpha.
1. Determine the activity rate for each activity. Enter these rates in the Activity Rate columns.*
2. Use the activity rates in (1) to determine the total and per-unit activity costs associated with Alpha.*
*If required, round all per-unit amounts to the nearest cent.
Alpha
Activity Activity-
Base Activity Activity
Usage X Rate = Cost
Production
Setup
Material handling
Inspection
Product Engineering
Total activity cost
Number of units
Activity cost per unit

Points:

0 / 28

Feedback

Check My Work

Calculate for each activity:

Total Activity Cost Total Activity-Base Usage = Activity Rate

Calculate for each product:

Activity-Base Usage x Activity Rate from Req. (1) = Activity Cost; Sum all activity costs per product to determine a total and divide the total overhead by budgeted units to derive the activity costs per unit for each product.

Activity Table - Beta

Shaded cells have feedback.

Complete the Activity Table for Beta.
1. Determine the activity rate for each activity. Enter these rates in the Activity Rate columns.*
2. Use the activity rates in (1) to determine the total and per-unit activity costs associated with Beta.*
*If required, round all per-unit amounts to the nearest cent.
Beta
Activity Activity-
Base Activity Activity
Usage X Rate = Cost
Production
Setup
Material handling
Inspection
Product Engineering
Total activity cost
Number of units
Activity cost per unit

Points:

0 / 28

Feedback

Check My Work

Calculate for each activity:

Total Activity Cost Total Activity-Base Usage = Activity Rate

Calculate for each product:

Activity-Base Usage x Activity Rate from Req. (1) = Activity Cost; Sum all activity costs per product to determine a total and divide the total overhead by budgeted units to derive the activity costs per unit for each product.

Activity Table - Omega

Shaded cells have feedback.

Complete the Activity Table for Omega.
1. Determine the activity rate for each activity. Enter these rates in the Activity Rate columns.*
2. Use the activity rates in (1) to determine the total and per-unit activity costs associated with Omega.*
*If required, round all per-unit amounts to the nearest cent.
Omega
Activity Activity-
Base Activity Activity
Usage X Rate = Cost
Production
Setup
Material handling
Inspection
Product Engineering
Total activity cost
Number of units
Activity cost per unit

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Auditing Concepts And Methods

Authors: McGraw-Hill

1st Edition

0074701266, 978-0074701263

More Books

Students also viewed these Accounting questions