Metal Company budgeted $575,000 manufacturing direct wages, 2,000 direct labor hours, and had the following manufacturing overhead: Overhead Cost Pool Budgeted Overhead Cost Budgeted Level
Metal Company budgeted $575,000 manufacturing direct wages, 2,000 direct labor hours, and had the following manufacturing overhead:
Overhead Cost Pool | Budgeted Overhead Cost | Budgeted Level for Cost Driver | Overhead Cost Driver | |
---|---|---|---|---|
Materials handling | $ 156,000 | 5,200 | pounds | Weight of materials |
Machine setup | 17,700 | 590 | setups | Number of setups |
Machine repair | 1,600 | 32,000 | machine hours | Machine hours |
Inspections | 21,600 | 360 | inspections | Number of inspections |
Requirements for Job #971 which manufactured 4 units of product:
Direct labor | 20 | hours |
---|---|---|
Direct materials | 330 | pounds |
Machine setup | 40 | setups |
Machine hours | 17,000 | machine hours |
Inspections | 15 | inspections |
Using Activity-Based Costing, overhead cost assigned to Job #971 for machine setup is:
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started