Mini - Project 9 : Mid - Size IT Project Mini - Project Overview Project Submission Steps You work for a mid - size electronics

Mini-Project 9: Mid-Size IT Project
Mini-Project Overview
Project Submission Steps
You work for a mid-size electronics company called Globex. The environment is hybrid Azure AD, with Office 365 for email and collaboration. Azure is used for user
authentication and SSO (single sign-on), and a few on-premise domain controllers are strategically located around the world. Currently, all of the desktops and laptops are running Windows 10 Enterprise, version 20H2. Microsoft will be ending active support and security support for this version in ten months, so management wants to upgrade these systems to Windows 10 Enterprise, version 21H2.After seeing the initial project presentation, the CIO and his lieutenants have signed off
on the plan. It now needs to go to the Project Management Office (PMO). A project
management office is a group or department within a business, government agency, or
enterprise that defines and maintains standards for project management within the
organization. The PMO strives to standardize and introduce economies of repetition in
the execution of projects.
Your assignment is to create a Gantt chart showing the project plan from beginning to
end, including Hypercare (see note below).
Note: After a software launch, software providers go into hypercare by providing
extra support to their users. This additional support helps new and existing
customers understand how to use the new product, service, feature, or program.
As far as cost goes, the project has been fully funded, so dont worry about tracking
expenditures. Just focus on the timeline and milestones.
Submission: You may use Google Sheets to create the Gantt chart.
Gantt Project
The project must begin on June 1, and end on February 1(8 months).
The number of PCs and laptops to be upgraded is 800.
While many applications have been moved to the cloud, there are still 15 custom
applications that must be able to run without issues on the upgraded Windows
10 version.
Security configuration must match CIS Level 1 controls, although 100 of the
machines will have to match Level 2.
Upgrading the hardware is not in scope for this project, so the upgrade will need
to work on the existing hardware.
Milestones for each major phase must be shown on the chart.
Key Considerations:
Globexs fiscal year is the same as the calendar year, so 1/1/ to 12/31. You will
need to factor in the month-end, quarter-end, and year-end financial closes in
order to avoid disrupting the financial close process.
The machines are located in the U.S., Brazil, the U.K., Germany, and France. This means different languages, time zones, and holidays.
Test cases will be dependent on feedback from key users, so you will have to
interview them (remotely of course).
Key Tasks:
Use the following phases and time estimates for your chart, but feel free to modify them
as you see fit.
Planning (1 week)
Develop project plan
Identify stakeholders
Create kickoff materials
Conduct kickoff meeting
Design (1 month)
Gather requirements
Identify list of applications
Define the system and security configurations of the new Win 10 build
Develop test design
Develop test cases
Testing (4 months)
Develop test strategy and test plan
Functional testing
Integration testing
System testing
UAT (User Acceptance Testing)
Non-Functional testing
Performance testing
Reliability testing
Security testing
Deploy (3 months)
Phased rollout
Could be by country, department, or some other criteria)
Hypercare support

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Learn Mysql The Easy Way A Beginner Friendly Guide

Authors: Kiet Huynh

1st Edition

B0CNY7143T, 979-8869761545

More Books

Students also viewed these Databases questions