Question
Moon Company is manufacturing the plastic sheets into products A, B and C using three process that is mixing, processing and smoothing. Raw materials for
Moon Company is manufacturing the plastic sheets into products A, B and C using three process that is mixing, processing and smoothing. Raw materials for the plastic is first mixed then processed and finally smoothing.
The processing capacity varies for each process and the factory manager has provided the following data:
Processing time per meter in hours
Product-Red Product-Blue Product-Yellow
Mixing 0.50 0.50 0.40
Processing 0.25 0.40 0.25
Smoothing 0.40 0.25 0.25
The factory operating for 225,000 hours.
Identify the bottleneck process and explain why this process is described as a bottleneck
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started