MS.53 An office furniture manufacturer needs to calculate material requirements for one of its most popular tables. The graphic above shows the bill of material
MS.53 An office furniture manufacturer needs to calculate material requirements for one of its most popular tables. The graphic above shows the bill of material for this item. Below are the MRP tables for the top-level assembly (the Office Table Final Assembly) and one of its sub-assemblies (the Table-Top Assembly):
Office TableFinal Assembly 8/1 8/8 8/15 8/22 8/29 9/5 9/12 9/19 9/26
Gross Requirements 500 200 300 300 600 100
Scheduled Receipts
Projected On-Hand Inv. 440
Net Requirements
Planned Order Receipts
Planned Order Releases
Lead Time (in weeks) 1
Lot Size 150
Table-Top Assembly 8/1 8/8 8/15 8/22 8/29 9/5 9/12 9/19 9/26
Gross Requirements
Scheduled Receipts 70
Projected On-Hand Inv. 100
Net Requirements
Planned Order Receipts
Planned Order Releases
Lead Time (in weeks) 1
Lot Size 60
For theOffice Tableabove (the firstMRP table), what is theProjected On-Hand Inventoryin the week of 9/19?
For theOffice Tableabove, what are thePlanned Order Receiptsin the week of 8/8?
For theTable-Top Assemblyabove, what are theNet Requirementsin the week of 9/19?
For theTable-Top Assemblyabove, what are thePlanned Order Releasesin the week of 9/5?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started