Multiple Choice Assume that the amount of one of a company's fixed expenses in its flexible budget is $46,000. The actual amount of the expense
Multiple Choice Assume that the amount of one of a company's fixed expenses in its flexible budget is $46,000. The actual amount of the expense is $48,400 and the amount in the company's planning budget is $46,000. The spending variance for this expense is: $0. $2,400 U $2,400 F. $4,800 U