My boss and I could use your advice on our current project, she says. We seem to do a good job of developing activity lists
My boss and I could use your advice on our current project," she says. "We seem to do a good job of developing activity lists from the work breakdown structures we develop and sequencing activities. My boss takes that and comes up with estimates for all of the activities based on what he thinks is reasonable given the project deadline provided by the sponsor."
Karla gives you a pained look and admits, "For each of the three projects I've worked on with him, the sponsor has gotten extremely upset because the team has never hit a milestone. The sponsor has had to authorize additional money to complete the project on time in each case and has warned my boss that this can't happen for the project we've been assigned to now. What might we be doing wrong in developing our schedules, and how can we fix it?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started