Nash Construction Company uses the percentage-of-completion method of accounting. In 2020, Nash began work under contract #E2-D2, which provided for a contract price of $2,191,000.
Nash Construction Company uses the percentage-of-completion method of accounting. In 2020, Nash began work under contract #E2-D2, which provided for a contract price of $2,191,000. Other details follow:
| 2020 | 2021 | ||
Costs incurred during the year | $596,440 | $1,421,000 | ||
Estimated costs to complete, as of December 31 | 1,015,560 | 0 | ||
Billings during the year | 412,000 | 2,191,000 | ||
Collections during the year | 346,000 | 1,501,000 |
A. What portion of the total contract price would be recognized as revenue in 2020? In 2021?
B. Assuming the same facts as those above except that Hamilton uses the completed-contract method of accounting, what portion of the total contract price would be recognized as revenue in 2021?
C. Prepare a complete set of journal entries for 2020 (using the percentage-of-completion method)
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started