Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

NIBCO had planned to go live with the ERP project on December 1, 1997, the Monday after the Thanksgiving holiday.7 The baseline project schedule is

NIBCO had planned to go live with the ERP project on December 1, 1997, the Monday after the Thanksgiving holiday.7 The baseline project schedule is shown in Figure 8-12. The four phases (preparation, analysis, design, and implementation) were scheduled as shown with a post-live date of March 31, 1998, the actual end date of the SAP project. After the go-live date of December 1, 1997, the project team had to spend time on the project in post-production activities and quality assurance. The post-live activities also included: Check system performance on a daily basis; Validation of business processes and their configuration; Followup training for users; Signoffs; Add new application components; and Automating and improving business processes. NIBCO wanted to schedule the project closure dates with anticipated possible problems. The project leadership team spent a lot of time planning the end date. It developed extended versions of the schedule in order to mitigate the risk of possible extension; the following are the various scenarios of schedule proposed by the project team: 1. A first plan where the organization has to perform at a very superior level to attain the maximum performance possible that coincided with the baseline schedule; 2. A second plan where the organization has to perform at a standard level to attain the standard performance; and 3. A third plan where the organization can perform at a lower level to attain the minimum performance. All three plans are shown in Figures below. The difference in schedule between the first plan and the second plan was four months. The difference in schedule between the second plan and the third plan was another three months. On the whole, the project plan was presented to the stakeholders with a project schedule that varied from 18 months to 24 months.

image text in transcribed

What are the criteria and drivers that would ensure project completion for each one of the plans proposed in Figures CI-8-2 through CI-8-5?

Fiqure CI-8-1 ERP Project Timeline: Baseline 1996 1997 1998 oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Major Phases Preparation Analysis Design Implementation Post-Live Date Figure CI-8-2 ERP Projet: Critical Path 1996 1997 1998 Oct Nov Dec Jan Feb Mar Apr May JunAug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Major Phases Trained Core Team Trained End-Users Tested ERP Solution Stabilized Infrastructure Qualified On-site Support Level 2 Level 3 Basics Testers End-Users Unit Testing Stress Testing ystems Testin Support Available Figure CI-8-3 ERP Project Timeline: Maximum Performance 1998 1996 Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sepl Oct 1997 Major Phases Preparation Analysis Design Implementation Post-Live Date Fiqure CI-8-4 ERP Project Timeline: Standard Performance 1996 1997 1998 Major Phases Preparation Analysis Design Implementation Post-Live Date Figure CI-8-5 ERP Project Timeline: Minimum Perfomance 1996 1997 1998 Oct NovDecJan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jut Aug Sep Oct Major Phases Preparation Analysis Design Implementation Post-Live Date

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Databases And Python Programming MySQL MongoDB OOP And Tkinter

Authors: R. PANNEERSELVAM

1st Edition

9357011331, 978-9357011334

More Books

Students also viewed these Databases questions