Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

On 1 January 2020, ABD Ltd signed a contract worth $6,000,000 to construct a light rail. The complex was to be built over three years,

On 1 January 2020, ABD Ltd signed a contract worth $6,000,000 to construct a light rail. The complex was to be built over three years, with progress payments of $2,000,000 to be made at the end of each year. Estimated costs were $4,500,000 and the following costs incurred and paid by ABD Ltd were in accordance with estimates and represented the percentage completed in each year (Assume no tax): $1,000,000 in 2020, $1,250,000 in 2021, and $2,250,000 in 2022. The project will be completed in December 2022.

Using the percentage of completion method, how much profit will ABD report for the financial year ended 31 December 2022? (assume for this question, the financial year starts on 1 January 2022 and ends on 31 December 2022) (1 mark)

In your answer, include numbers only. No text, no commas, no signs or symbols etc.

$ Answer

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Managerial Accounting

Authors: James Jiambalvo

4th edition

9780470546888, 9780470333341, 470546883, 470333340, 978-0470578797

More Books

Students also viewed these Accounting questions

Question

When is it appropriate to use a root cause analysis

Answered: 1 week ago