On February 1 , 2 0 1 7 , Tanks A Lot obtained a contract to build a large municipal aquarium. The aquarium was to
On February Tanks A Lot obtained a contract to build a large municipal aquarium. The aquarium was to be built at a total cost of $ and was scheduled for completion by September One clause of the contract stated that Tanks A Lot was to deduct $ from the $ billing price for each week that completion was delayed. Completion was delayed weeks, resulting in a $ penalty. Tanks A Lot uses the percentage of completion method to account for revenue. Below are the data pertaining to the construction period:
Costs incurred during year
Estimated costs to complete
Progress billings to date
Cash collected to date
Calculate the total revenue recognized, total expenses recognized, and total gross profit recognized in each year.
Hints:
For revenue: calculate the percentage complete the project is each year based on the costs incurred to date in comparison to total estimated costs for the project and apply it to total revenue for the project
For gross profit: subtract the current year costs from the current year revenue
For years and : consider what was recorded before
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started