On January 1, Year 1, Big Co. enters into a contract with a customer to build a bridge on the customer's land for $2,500,000. The

On January 1, Year 1, Big Co. enters into a contract with a customer to build a bridge on the customer's land for $2,500,000. The construction of the bridge is expected to be completed at the end of Year 3. Big Co. determines that the progress toward completion of the bridge is reasonably measurable using the input method based on costs incurred. At contract inception, Big estimates that the expected total cost of construction will be $1,700,000. Below are the (1) actual costs incurred during each year, (2) expected costs to complete the construction, and (3) amounts billed to the customer?

Costs incurred each year

Year 1 $700,000

Year 2 $500,000

Year 3 $800,000

Costs expected in the following years

Year 1 $1,300,000

Year 2 $675,000

Year 3 $ 0

Amounts billed to (and paid by) the customer each year

Year 1 $700,000

Year 2 $950,000

Year 3 $850,000

What amount of gross profit on this contract is recognized by Big in its Year 3 income statement?

a.$500,000

b.$50,000

c.$100,000

d.$166,667

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Essentials Of Accounting For Governmental And Not-for-Profit Organizations

Authors: Paul Copley

14th Edition

1260570177, 978-1260570175

More Books

Students also viewed these Accounting questions