On June 15, 2018, Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington, D.C., for $270 million. The expected

On June 15, 2018, Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington, D.C., for $270 million. The expected completion date is April 1, 2020, just in time for the 2020 baseball season. Costs incurred and estimated costs to complete at year-end for the life of the contract are as follows ($ in millions):

2018 2019 2020
Costs incurred during the year $ 50 $ 100 $ 60
Estimated costs to complete as of December 31 150 90

Required: 1. Compute the revenue and gross profit will Sanderson report in its 2018, 2019, and 2020 income statements related to this contract assuming Sanderson recognizes revenue over time according to percentage of completion. 2. Compute the revenue and gross profit will Sanderson report in its 2018, 2019, and 2020 income statements related to this contract assuming this project does not qualify for revenue recognition over time. 3. Suppose the estimated costs to complete at the end of 2019 are $100 million instead of $90 million. Compute the amount of revenue and gross profit or loss to be recognized in 2019 using the percentage of completion method.

Percentages of completion
Choose numerator Choose denominator = % complete to date
Actual costs to date Estimated total costs
2018 $50 $200 = 25.00%
2019 $150 $240 = 62.50%
2020 100.00%
2018
To date Recognized in prior years Recognized in 2018
Construction revenue $67 $0 $67
Construction expense $50 $0 $50
Gross profit (loss) $17 $0 $17
2019
To date Recognized in prior years Recognized in 2019
Construction revenue $169 $67 $102
Construction expense $150 $50 $100
Gross profit (loss) $19 $17 $2
2020
To date Recognized in prior years Recognized in 2020
Construction revenue $270 $169 $101
Construction expense $210 $150 $60
Gross profit (loss) $60 $19 $41
Year Revenue recognized Gross Profit (Loss) recognized
2018 $67 million $17 million
2019 $102 million $2 million
2020 $101 million $41 million
Percentages of completion
Choose numerator Choose denominator = % complete to date
Actual costs to date Estimated total costs
2019 $150 $250 = 60.00%
2019
To date Recognized in prior Years Recognized in 2019
Construction revenue $160 $67 $93
Construction expense $152 $50 $102
Gross profit (loss) $12 $17 $(5)

Requirement 2 and every red cell and in bold is incorrect, everything else is right. Please help as fast as you can.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Statistical Techniques For Analytical Review In Auditing

Authors: Kenneth W. Stringer, Trevor R. Stewart

1st Edition

047186076X, 978-0471860761

More Books

Students also viewed these Accounting questions